In addition to this participation guide, please review the complete Odyssey user guides and FAQs to troubleshoot
any issues, or reach out to the Odyssey support team via the support chat box in the bottom right corner of the application.
- Create a Mini-Grid Project.
In the load module, you will provide information on the number and type of customers as well as the projected load profile. Learn more about creating a load assessment.

The Costs module is a place to track and categorize project capital and operating expenditures.
These will be pulled into the Financials module and used to calculate project financial performance metrics. Learn more about tracking costs.
RequirementIn the Financials module, you will enter project-level sensitivities and account for ramping/growth rates for your load assessment.
The financial page uses all the information you entered into Odyssey to calculate key financial metrics. Learn more about calculating project financials.

You are required to upload all site-specific documents in the Project Application tab.
Go to the Documents Upload section in the application form.
Drag and drop your files into the upload area, or click Browse to select files from your device.
Ensure you upload all required supporting documents in this section to successfully submit your application.
To upload additional files not listed in the Documents Upload section:
Click on the Files tab.
Upload your additional documents by clicking Upload Files and selecting the files you wish to add.
To submit your project:
Navigate to the Project Submission module.
Click the Submit Project to Program button.
Verify that all required documents in the Project Application tab are uploaded, as incomplete uploads will prevent submission.
Below is a description of the project application statuses set by the program managers. You can use this information to track the status of your application:
Under Review
Your application is currently being reviewed by the program managers.
Incomplete
Your site-specific application is incomplete and requires additional information. Your project has been reopened for editing.

Approved/Grant Agreement Under Review
Your application has been reviewed and accepted. The grant agreement is currently under review.
Grant Agreement Signature
The grant agreement for your project has been signed.
Commissioned
The project has been commissioned and is in progress.
Declined
Your application has not been approved for the program.
Cancelled
The project has been cancelled
Financing Secured
Once you have secured financing needed to begin purchasing materials for and constructing your site, set the status of your project to "Financing Secured"
to update the program administrators (REA) on your project progress.
Purchase Order Assets
Once you have placed an order for the purchase of materials for the site, set the status of your project to "Purchase Order Assets"
to update the program administrators on your project progress.
All Goods Received (Cleared Customs)
Once you have received the materials and cleared them.
Installation (All Goods on Site)
Once all materials required for construction are at the site and you are able to begin the installation of the mini-grid components.,
set the status of your project to "Installation (All Goods on Site)" to update the program administrators on your project progress.
Under Construction
Once you have begun construction on your project, set the status of your project to "Under Construction"
to update the program administrators on your project progress.
Commissioned
Once your solar plant is connected to the DisCo grid, NEMSA has inspected the site, and at least 80% of your planned connections are connected with meters integrated on Odyssey, set the status to "Commissioned" and upload the Milestone 1 documents listed in Section 6. Learn more here.

Customers Connected
Once customers have begun using power at the site, set the status of your project to "Customers Connected" to update the program administrators on your project progress.

| Feeder band | Grant rate |
| Band C | USD 750 per kWp |
| Band D | USD 950 per kWp |
| Band E | USD 1,000 per kWp |

Example
A Band E project is approved for 1,000 kWp in the grant agreement, making it eligible for up to 1,000 kWp x USD 1,000 = USD 1,000,000.
| Milestone 1 | Milestone 2 |
|
|
Total grant disbursed (if all conditions are met): USD 900,000.

Once your site has been commissioned, please complete your meter integration as soon as possible so your data will be available when you are ready to complete remote verification.
Note: When creating the Integration on Odyssey, please ensure the Level of integration is Project level and the Data Set is Meter Metrics. Reach out to the Odyssey support team incase of any questions.
You will upload connections and complete remote verification in the Connections module of each project. Learn more about completing remote verification and submitting your connections.
To verify your connections;
Select the checkbox next to each connection you would like to submit
Select Verify
View your connections status
Once you select 'Verify', the verification process will be initiated and the status of each of them will be displayed. Review the meaning of each status below:
Verification in progress
The request to verify the connection has been sent.
Meter Reading not found
No data was found for the meter. Please check your integration again
Data out of date range
Consumption was found, but not within the date range of the rule (e.g. Consumption is greater than zero but doesn't meet the 90-day date range)
Didn’t meet requirements
Consumption is equal to 0
Error during verification
An unexpected error occurred.
Verified
Verification was successful
Once you have submitted connections, the program administrators will review your connections and either mark the connections as Approved, Paid, or Rejected. You can view a summary of the status of all connections in the summary at the top of the Connections module and will be notified by email of any connection status updates.
Not Submitted
Connections are uploaded to Odyssey but not submitted.
Submitted Connections
Investor has received the connections.
Approved Connections
Investor has approved the connection.
Paid Connection
The program administrator has processed the connection as part of a grant disbursement.
Rejected Connections
The investor received the connection and there was a reason the connection was refused.
You can rectify the connection (ex: adding missing information) and submit again if appropriate. Please check the Messages section of your project for more information from the program administrator.
You can communicate with the Program administrators
Navigate to the Messages module in your project.
Write your message
Click on Submit to send it.