The AfDB NEP Minimum Subsidy Tender (MST) program is powered by Odyssey exclusively for all tender-related activities. Submissions outside of the platform will not be accepted.
In addition to this participation guide, please review the complete Odyssey user guides and FAQs to troubleshoot any issues, or reach out to the Odyssey support team via the support chat box in the bottom right corner of the application.
Odyssey enables you to integrate operating data in the data integrations section of Odyssey.
For remote verification of connections, Odyssey automatically checks your meter and payment data integrated with Odyssey to verify that your connections have been supplied with electricity and meet program requirements. Learn more about setting up a data integration.
Once your site has been commissioned, please complete your meter integration as soon as possible so your data will be available when you are ready to complete remote verification.
Note: When creating the Integration on Odyssey, please ensure the Level of integration is Project level and the Data Set is Meter Metrics. Reach out to the Odyssey support team in case of any questions.
Once you have connected the customers, you are required to upload the proof of customer connections on the Odyssey platform. To do this:
Navigate to the Connections module of the claim.
Select the Download Template button to download an Excel template where you can input your proof of customer connections. A description of the data you should include in each column is outlined below:
Once complete, upload the completed Excel template, then submit your connections:
Select the checkbox next to each connection you would like to submit.
Select the Submit button.
Choose Submit Selected Connections or Submit All (Filtered) Connections from the dropdown menu.
Verify that all connections were submitted in the summary panel at the top of the page.
You will upload connections and complete remote verification in the Connections module of each project. Learn more about completing remote verification and submitting your connections.
MST Program Requirement: A connection will be considered verified if Odyssey finds the total consumption is greater than 0 kWh.
Verify your Connections
To verify your connections:
Select the checkbox next to each connection you would like to verify.
Select Verify.
View your connections status.
Once you select 'Verify', the verification process will be initiated and the status of each connection will be displayed. Review the meaning of each status below:
Verification in progress
The request to verify the connection has been sent.
Meter Reading not found
No data was found for the meter. Please check your integration again.
Data out of date range
Consumption was found, but not within the date range of the rule.
Didn't meet requirements
Consumption is equal to 0.
Error during verification
An unexpected error occurred.
Verified
Verification was successful.
Once you have submitted connections, the program administrators will review your connections and either mark the connections as Approved, Paid, or Rejected. You can view a summary of the status of all connections in the summary at the top of the Connections module and will be notified by email of any connection status updates.
Not Submitted
Connections are uploaded to Odyssey but not submitted.
Submitted Connections
Investor has received the connections.
Approved Connections
Investor has approved the connection.
Paid Connection
Investor has given the connection a tier, assigned a payout, and paid for the connection.
Rejected Connections
The investor received the connection and there was a reason the connection was refused. You can rectify the connection (e.g. adding missing information) and submit again if appropriate. Please check the Messages section of your project for more information from the program administrator.
You can communicate with the Program administrators:
Navigate to the Messages module in your project.
Write your message.
Click on Submit to send it.